8.10.18

Posted by Eric Driessen on 8/10/2018

Construction continues to be on time and on budget. Items completed thus far; new sewer lines, drain in south parking lots, light bases installed, walls for performance center/gym almost complete, footprint for 12 classrooms and office area done, retaining wall around basketball court and a few other items.   The bus lane and walkway on the north side of the elementary planned to be done before school begins.  Once the performance walls are complete, they will begin the classroom walls.

cons   cons   cons    cons

1. bus lane/west side elem.  2.retaining wall around hoop ct  3.last bit of wall for perf. ctr  4.gym, lockers & stage to left